JSC “Rīgas elektromašīnbūves rūpnīca” successfully implements the 2nd stage of the project “The Complex solutions to increase of energy efficiency at JSC Rīgas Elektromašīnbūves Rūpnīca”.
By 07.07.2020, the company acquired a milling-centering machine, a compound punch for generator stator sheet preparation, an air compressor, carousel turning machine, drying oven, climatic equipment kit for product strength testing, climatic test chamber, as well as part of planned LED lighting devices was purchased. Renovation works in all three buildings have been completed.
The horizontal milling center has also been supplied, but testing and commissioning of the equipment has not yet been completed due to the Covid-19 pandemic. Currently, the equipment supplier technician from Italy is in Riga and carries out the assembly, testing and aligning work of the plant. The equipment is scheduled to be put into service within 3-4 weeks.
The project is co-financed by the Central Financial and Contract Agency and the Cohesion Fund.